Planning agency: International Highway Construction Corporation
Executing agency: Far East Development Co., Ltd.
With a construction period of about 500 years since the start of the survey inclined shaft, the construction of the first and second surveyed inclined shafts was almost completed, and the stage of temporary equipment replacement, which was originally planned, was reached.Temporary equipment for the second phase construction, especially the capacity of the hoisting winch, etc. corresponds to the scale of excavation length of about 1,410 m, while for the third phase construction and below, the design inclined shaft length, temporary materials from XNUMX m, etc. The ability to unwind is required.
In addition, it is necessary to plan the expansion of power receiving equipment, water supply equipment, drainage equipment, air supply equipment, ventilation equipment, etc.In addition, along with the extension of construction, it will be necessary to construct new muddy water treatment facilities and injection facilities for flooding.However, if it is required to continue excavation for the time being, it is considered possible by changing the hoisting winch power receiving equipment and adding some other equipment.
The equipment (PUC-500T) of about XNUMX m until the second phase construction is as shown after the item, but in the third phase and below, the equipment specification conditions differ greatly as the excavation extension increases.
The outline is shown below.
XNUMX-XNUMX Basic conditions |
Mine inclination angle:☆ θ = 14 ° 02' Diagonal length:☆ L¹ = 1400m Hoisting distance:☆ L² = 1500m Weight of cargo: Mining vehicle 2700kgf / vehicle x 5400 vehicles = XNUMXkgf Mining vehicle contents: 1.7tf / m³ x 4.3m³ x 15300 = XNUMXkgf Car: 12-seater Hoisting speed:☆ υ = 150m / min ☆ mark is common to both mining car winding and human car winding |
||
---|---|---|---|
XNUMX-XNUMX Equipment specification |
2-2-1 Mining car hoisting machine |
XNUMX) Loading condition |
W¹ Mining vehicle weight 2700kgf x 5400 = XNUMXkgf Load 1700kgf / m³ x 4.5m³ / car = 15300kgf ∴W¹ = 5400 + 15300 = 20700kgf W² Wire rope own weight 2.59kg / m × 1500 = 3885kgf |
XNUMX) Rope tension |
P=W¹(sinθ+μcosθ)+W²(sinθ+μ′cosθ)=20700(sin14°02′+1/60cos14°02′)+3885(sin14°02′+1/10cos14°02′)=5430+1320=6750≒6800kgf And |
||
XNUMX) Motor output |
![]() |
||
XNUMX) Rope factor of safety |
![]() Rope diameter used: φ25 (Toughrop) Breaking force used: BS = 50.1 tf |
||
XNUMX) operation |
The operation shall be manual operation from the winding room. However, when operating in a certain section (wellhead → bottom), acceleration → full speed → deceleration → stop is automatically performed.Since the face part changes with excavation, the stop switch and the excess switch will be relocated. |
||
XNUMX-XNUMX-XNUMX Car hoisting machine | XNUMX) Loading condition |
W¹ Vehicle weight 7160kgf (including hanging hardware)![]() W² Wire rope own weight 1.99 × 1500m = 2985 kgf |
|
XNUMX) Rope tension |
P = W¹ (sinθ + μcosθ) + W² (sinθ + μ ′ cosθ) = 2070 + 1013 = 3083 ≒ 3100kgf. | ||
XNUMX) Motor output |
![]() |
||
XNUMX) Rope factor of safety |
![]() Rope diameter used: φ22 (Toughrop) Breaking force used: BS = 38.5 tf |
||
XNUMX) operation |
Basically, Similar to mining car hoisting machine |
XNUMX) Electric capacity | ① Compressor | 150kw | |
---|---|---|---|
② Repair shop | 20kw | ||
③ Blower | 60kw x 120 = XNUMXkw | ||
④ Unwinder | A) | 220kw (for scraping) | |
B) | 110kw (for human cars) | ||
⑤ Plant equipment | 22kw | ||
⑥ Sprayer | 11kw | ||
⑦ Jumbo drill | 220kw | ||
⑧ Pumping pump | 15kw | ||
⑨ Lighting power | 40kw | ||
⑩ Other | 20kw | ||
Total | 948kw |
The total power used in this construction is 948kw, but the plant equipment (22kw) and sprayer (15kw) are not used during excavation.Also, since the jumbo drill and the hoisting machine for scraping are not used at the same time, it is considered that 700kw of contract power is sufficient.
* The construction has been completed and one track has been removed.
* Third phase construction site (center is the entrance to the inclined shaft)
* Two upper and lower slide carriers
* The white building is equipped with a hoisting machine.
Overview of the Japan-Korea Tunnel