Kyushu Scene News

Improving the roadway of the Iki/Ashibe slope shaft - August issue from the site

■Iki/Ashibe Diagonal Mine The road was prepared and the survey was finally carried out in preparation for the installation of the tunnel entrance.Dense forest
clearing and road construction at the planned site of Iki's Ashibe Diagonal Mine were carried out from July 29th to August 2nd. The clearing and road-making work on the 30,000 square meter site, which had turned into a dense forest over the past 40 years, has come to an end. Finally, we were able to drive around the premises in a light truck.

 

After cutting down trees to the width of the road (5 to 6 meters), we cut down bamboo roots with a mower, cut out tree stumps with a saw, and cut out the roots of large trees with a chainsaw to create a path. In addition, stones were collected and spread on the slope with steps, and soil was carried using a unicycle and filled in to create a gentle slope so that light trucks could go up and down. After working hard for half a year, we were finally able to drive a light truck around the site of the planned Iki Ashibe Incline. Now, the technical committee can carry out on-site reconnaissance, survey, and create a plan for the Iki/Ashibe slope base. Finally, the technical committee will begin surveying in mid-August.

 

①Run north-south west of the prefectural road site

201508_1

 

②Upper entrance

There are three entrances to the site from the prefectural road: upper, middle, and lower.

201508_2

 

Upper entrance

If you turn left from the center back, you will reach the upper site of the planned mine entrance.

201508_3

 

③Lower entrance

201508_4

 

Lower entrance

A pit entrance is planned to be installed at the center of the site once it reaches the bottom.

201508_5

 